Cemetery Lane Paving and Slaughterhouse Bridge Rehab

This project will repair and repave the County portion of Cemetery Lane as well as perform critical maintenance work on the Slaughterhouse Bridge.

During critical bridge deck repairs and resurfacing, the bridge will need to be closed to all traffic for the safety of workers and the travelling public. These closures will be allowed from 9:00 AM-7:00 PM for up to 10 working days. If the condition of the bridge is worse than anticipated, the closure period and duration may need to be extended.


Bridge Work:

  • Bridge Deck repairs
  • New Waterproofing Membrane
  • New Asphalt Pavement Surfacing
  • Bridge Railing Replacement
  • Various Concrete and Sidewalk Repairs

Roadway Work:

  • Spot Full Depth Pavement Repairs
  • Asphalt Milling and Repaving
  • Guardrail Replacements

Project:  

April 6- June 12


Full Bridge Closure: 

9:00 AM-7:00 PM

April 10 - April 23

While not anticipated, unforeseen bridge conditions could require occasional extensions or additional closure days.


Cemetery Lane and Slaughterhouse Bridge Map
  1. 1 Cemetery Lane Paving Project I
  2. 2 Cemetery Lane Paving Project II
  3. 3 Cemetery Lane Paving Project III
  4. 4 Cemetery Lane Paving Project IV
Slaughterhouse Bridge and Rio Grande Trail  Bike Ped Detour